We use own and third-party cookies to improve our services and show information related to your preferences by analyzing your browsing habits. If you continue browsing, it shall be deemed you are accepting their use.
More info Understood

Grupo Cobra

  • Engineering and Consulting
      • Project design and consulting in the areas of environment, transportation, traffic, renewable energy, civil works and structures, control of industrial processes, lighting, communications, railway systems, and security systems.
      • Work management and supervision.
      • Information Technology.
  • Instrumentation and Control Systems
  • Communication Systems and Networks
  • Security, Electronic and PCI Systems

Featured Projects

Substations complex for wind power evacuation in: LA LORA 400kV, LA COCULINA 400/132Kv, LA LAGUNA 132/20kV Y LA LAGUNA COCULINA 132/20kV

Location:
Burgos, Spain

Detailed description:

- Realized by INTRADEL
- 400kV substation in tow corridors, plus another future corridor, in breaker and a half setup.
- A 400/132kV 450MVA autotransformer with three single-phase units, plus one reserve.
- Three 132kV substations with shared simple bar configuration, two of them also with 20kV cells.