Live-line laying of conductors and optical fiber

Location:
Spain, Camerún y Venezuela

Detailed description:

More than 2,500km of OPGW cable to replace the conventional guard cable with TET techniques in 400kV lines.

Cameroon: Supply and live-line installation of ADSS cable with 24 fibers in 225kV and 90kV lines. 375km in total.

Venezuela: Live-line laying of OPGW cable to replace the existing Alumoweld cable, in 230 and 800kV lines (603km in total.)