220 and 225kV Lines

Location:
India & Cameroon

Detailed description:

Haryana Project (India):
Turnkey construction of 4 220kV lines, double circuit (155km in total), Fatehabad-Chormar/Chormar – Rania/Ahir-Dhanonda/Badshahpur-Bhiwadi-Rewan, and 6km of 220kV line, single circuit, Dadri-Riwari

Bekoko-Nkonsamba Project (Cameroon):
Turnkey construction of: 113km of 225kV line, with a total of 290 self-supporting towers, 3 conductors per phase in ACSR 366mm2, and guard cable PHILOX 94mm2 and 1 OPGW cable with 48 fibers.